HSKEPP  Phase 1 · Combined Programme
Combined Programme Progress

Hung Shui Kiu Effluent Polishing Plant Phase 1

DC202411Civil Engineering Works DE202409E&M Installation Works
Press → or click to begin · P presentation mode
01Project Overview

Where are we now?

05Integrated Programme

Both contracts, one timeline

02Progress Status

How much is built?

Drag along the curve or press play. The model shows what has been built by the selected date: actual progress up to the data date, then the current forecast.

06Civil / E&M Interfaces

Which Civil works are affecting E&M?

07Critical Activities

What is critical?

Select an activity
08Look-Ahead Programme

The next 4 weeks

09Key Milestones

Which milestones are next?

Hollow markers are the contract key dates, which serve as the baseline. Solid markers are the current planned dates. Select a milestone to see what leads into it.

10Completion Outlook

When will it finish?